Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Poloidal field magnets | The last ring

    As the massive ring-shaped coil inched its way from the Poloidal Field Coils Winding Facility, where it was manufactured, to the storage facility nearby where i [...]

    Read more

  • Heat rejection | White "smoke" brings good news

    Like a plume of white smoke rising from a cardinals' conclave to announce the election of a new pope, the tenuous vapour coming from one of the ITER cooling cel [...]

    Read more

  • WEC 2024 | Energy on centre stage

    The global players in the energy sector convened in Rotterdam last week for the 26th edition of the World Energy Congress (WEC). The venue was well chosen, wit [...]

    Read more

  • Fusion world | The EU blueprint for fusion energy

    The EU Blueprint for Fusion Energy workshop, convened by the European Commission's Directorate-General for Energy, brought together key stakeholders in the fiel [...]

    Read more

  • Neutral beam injection | ELISE achieves target values for ITER

    Researchers at the Max Planck Institute for Plasma Physics in Garching, Germany, have generated the ion current densities required for ITER neutral beam injecti [...]

    Read more

Of Interest

See archived entries

Feeders

Multi-lane thruways into the machine

The ITER superconducting coils thrive on a simple diet of electrical power and cooling fluids. The industrial installation on site is scaled to provide both, but the challenge is in the delivery. How do you "feed" 10,000 tonnes of magnets distributed among dozens of massive individual components in the crowded environment of the machine? The answer is: "feeders."

On January 26 2021, the coil terminal box of the feeder serving toroidal field coils #12 and #13 was placed into position in the gallery at the lowest level (B2) of the Tokamak Building. From left to right: ITER Feeders Mechanical Engineer Zhou Tingzhi and Feeders Assembly Responsible Engineer Giobatta Lanfranco. (Click to view larger version...)
On January 26 2021, the coil terminal box of the feeder serving toroidal field coils #12 and #13 was placed into position in the gallery at the lowest level (B2) of the Tokamak Building. From left to right: ITER Feeders Mechanical Engineer Zhou Tingzhi and Feeders Assembly Responsible Engineer Giobatta Lanfranco.
From the outside, a magnet feeder looks like a large box from which a fat pipe emerges that decreases in cross section the closer it gets to the centre of the machine. Arranged in a circle at both the lower and upper levels of the ITER Tokamak, the 31 magnet feeders* are like giant syringes all aiming in the same direction.

As the feeder boxes sit outside the machine in the Tokamak Building galleries—and as the pipes cross through first the bioshield and then the cryostat—one cannot, except in drawings, take in the whole expanse of the feeder system. Similarly, the outside appearance of individual feeders translates nothing of the extreme complexity inside: magnet feeders are among the most sophisticated of all ITER components and, being the lifeline of the entire ITER magnetic system, among the most strategic.

Whichever coil it connects to, a feeder is made of three main segments: a coil terminal box, a cryostat feedthrough and an in-cryostat feeder. Once assembled, these segments form a system 30 to 50 metres long that extends from the galleries to the heart of the machine.

The complexity inside defies description: busbars transporting current run alongside piping that distributes and recovers cryogenic fluids at different temperatures ... all carefully insulated by vacuum ducts and actively-cooled thermal shields. This multi-lane thruway into the machine also accommodates high and low-voltage instrumentation cables and hardware.

Twenty-one feeders, out of a total of 31, will be installed in the lower basement level (B2) of the Tokamak Building. In green at centre-left is the feeder serving toroidal field coils #12 and #13. (Click to view larger version...)
Twenty-one feeders, out of a total of 31, will be installed in the lower basement level (B2) of the Tokamak Building. In green at centre-left is the feeder serving toroidal field coils #12 and #13.
Procured by China and manufactured at the Institute of Plasma Physics, Chinese Academy of Sciences (ASIPP), each feeder segment is delivered to ITER fully instrumented and, following onsite inspections and testing, ready for assembly—in all more than 1,600 tonnes of equipment and 93 large components plus auxiliaries.

A little more than two years ago, in December 2018, the first magnet feeder element was installed in the assembly pit. Designed to serve poloidal field coil #4, one of the largest of the machine's ring-shaped magnets, the ''captive'' feedthrough needed to be brought into position before the completion of the cryostat base support ring.

In a delicate and spectacular operation, the 8-metre-long, 4.5-metre-tall, 7.5-tonne elbow-shaped component had to be introduced into the pit through the bioshield roof and inserted into the slim opening that had been left in the crown concrete for this purpose.

The upper level (L3) of the Tokamak Building will accommodate 10 feeders, including those connected to the central solenoid. (Click to view larger version...)
The upper level (L3) of the Tokamak Building will accommodate 10 feeders, including those connected to the central solenoid.
In December 2020, the cryostat feedthrough for the feeder serving toroidal field coils #12 and #13 was inserted into its designated position. One month later, the corresponding coil terminal box was positioned in the gallery at the lowest level (B2) of the Tokamak Building. This time, the massive component entered through a large opening in the Tritium Building and was moved along the gallery floor by means of roller skates underneath the transport frame.

The three feeder segments that are now in place inside the Tokamak Building are just a fraction of the elements required for the complete system. As components are delivered from China, installation will progress clockwise, first at the lowest B2 level, which accommodates 21 feeders, later at the upper L3 level for the remaining 10.

The feeder team has now established a robust installation plan and is proceeding on schedule. Next in line is the coil terminal box for PF #4, to be positioned parallel to the box recently installed, followed by the cryostat feedthrough and the valve box for one of the three feeders exclusively dedicated to cooling the coil structures.

* Of the 31 feeders to be installed (21 at lower level, 10 at upper level), two are exclusively dedicated to instrumentation signals and three to the cooling of coil structures. All others carry current and coolant to magnets.



return to the latest published articles