Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Sub-assembly tools

One foot inside

The twin Korean giants already have a foot inside the Assembly Hall—literally.

The giant's foot is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It belongs to one of the formidable handling machines that will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments. (Click to view larger version...)
The giant's foot is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It belongs to one of the formidable handling machines that will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments.
The foot—or "bottom inboard column" in ITER parlance—is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It is one of the four segments that, once stacked, will form the central column (and the rotation axis) of the first sector sub-assembly tool (SSAT-1)

Formidable handling machines, twin SSAT tools towering 22 metres above ground will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments.

Preparation for the erection of the first tool began two months ago, with the installation of the base plates for the rail tracks. The rails were temporarily put into position a few days ago to check the interfaces with the plates and to make sure that the bolt holes in both components are perfectly aligned.

Beginning next week installation will begin in earnest and last approximately four months. In March 2018, operational tests, including a load test of 310 tonnes, will be performed on SSAT-1. By that time, the second tool (under fabrication now in Korea) will have been delivered and the first assembly activities initiated.



return to the latest published articles