Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Also in this issue

  • Cross-section of a niobium-tin "billet" produced in Korea for ITER's toroidal field coils. Billets are drawn down to strands of less than one millimetre in diameter to form the building blocks of the superconductors. © Peter Ginter

    Superconductivity: it gets the current flowing

    To create the optimal conditions for fusion in a tokamak, the hot gas (plasma) must be confined in the centre of the vessel. This is the job of powerful magnet [...]

    Read more

  • Whatever their age or their knowledge of science and technology, the 1,300 visitors to ITER during the Open Doors Day 4 October were able to measure the scale of the project, its challenges and its potential.

    1,300 visitors "at home" at ITER

    When preparation work began on the platform in Saint-Paul-lez-Durance more than seven years ago, ITER was a mystery for many people in neighbouring towns and v [...]

    Read more

  • 14,000 m³ of concrete, 3,600 tons of rebar, 8 months of work—the "floor" of the Tokamak Complex was finalized on 27 August 2014.

    Last pour, first delivery

    Two milestones in ITER construction were achieved as summer 2014 drew to a close—the last pour of the Tokamak Complex basemat on 27 August and the delivery of [...]

    Read more

  • By reflecting the hues of the passing seasons, the mirror-like stainless steel will express, according to ENIA, "the precision of the research work being performed inside of the buildings."

    Mirror, mirror on the platform

    How much latitude does an architect have when considering how best to integrate the ITER buildings into the surrounding landscape? Not a lot, says architect S [...]

    Read more

Mag Archives

Twin giants to pre-assemble the vacuum vessel

As the doors of the Assembly Building open to admit the first vacuum vessel sectors shipped from manufacturing sites in Europe or Korea, two imposing custom-built tools will stand ready to receive them.

Six storyes high, with wings spreading 20 metres, the Sector Sub-Assembly tools will work side by side to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit, where they will be welded together to form the torus-shaped ITER vacuum chamber.

Six storyes high, made of 800 tons of steel, the Sector Sub-Assembly tools will work in concert to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit. (Click to view larger version...)
Six storyes high, made of 800 tons of steel, the Sector Sub-Assembly tools will work in concert to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit.
"It's far from a simple operation," says Emma Watson, an engineer who works within the Machine Assembly & Installation Section at ITER. "For each of the nine sectors, the complete sub-assembly operation will take five to six months." To optimize the overall schedule for the nine sectors, two identical tools are planned, each one capable of holding a sector on its end while positioning—and aligning—the associated components.

The sectors, which will travel from the factories in a horizontal position, will first have to be "upended" by a dedicated tool that is designed to lift the 440-ton (max) vacuum vessel sectors (7.6 x 6.5 x 13.7 metres) and the 310-ton toroidal field coils (9 x 3.7 x 17 metres) into their final, vertical orientation.

Then the Sector Sub-Assembly tools will take over, suspending each vacuum vessel sector from the top while carefully positioning and installing—via the rotary motion of the "wings"—the vacuum vessel thermal shields and two toroidal field coils. The sub-assemblies will be maintained in place as the remainder of the operations that must be completed on each 40° sector (such as the installation of some diagnostics, inter-connecting structures and cooling pipes) are carried out.

Standing shoulder to shoulder, two Sector Sub-Assembly tools will suspend the vacuum vessel sectors from the top while carefully positioning and installing—via the rotary motion of the ''wings''—the vacuum vessel thermal shielding and two toroidal field coils. (Click to view larger version...)
Standing shoulder to shoulder, two Sector Sub-Assembly tools will suspend the vacuum vessel sectors from the top while carefully positioning and installing—via the rotary motion of the ''wings''—the vacuum vessel thermal shielding and two toroidal field coils.
Made from 800 tons of steel, the 22-metre-tall tools will be capable of supporting, aligning, and stabilizing the vacuum vessel sectors and the toroidal field coils independently through a sophisticated array of precision actuators and sensors. "The assembly of the first sector will take the longest time, as assembly procedures based on the results of tests (involving partial component mockups) are honed via the experience gained as the sequences are performed for the first time on real components," says Emma. At different stages in the sub-assembly process, metrology surveys will be used to verify the components' positions. The final sub-assemblies, weighing a maximum of 1,200 tons, will be transferred by two overhead cranes operating in tandem to the Tokamak Pit.

As part of its procurement contributions to ITER, the Korean Domestic Agency is responsible for the design and fabrication of the Sector Sub-Assembly tool as well as 128 other purpose-built assembly tools.